Dutton Park to Salisbury Construction

Seven stations on Brisbane’s southside- Salisbury, Rocklea, Moorooka, Yeerongpilly, Yeronga, Fairfield and Dutton Park – will be rebuilt as part of the Cross River Rail project.

Station upgrades will include new overpasses and passenger lifts, accessible parking bays, new kiss’n’ride spaces, platform improvements and bike enclosures.

Stations rebuild progress

Construction and early works are now underway.

Find out more by using the links below:

Map showing work areas, temporary traffic changes on Fairlie Terrace and Dollis Street, Salisbury.

Salisbury station construction update - December 2024 and January 2025

On Monday 9 December 2024, Salisbury station will close to commuters to allow major construction to commence. The station will be closed to commuters until mid-2026. During December 2024 and January 2025, significant works will be undertaken including the demolition of platforms 1 and 2 including station buildings as major construction commences.

A map of the Clapham Yard work site.

Clapham Yard construction update - December 2024 and January 2025

In December 2024 and January 2025, UNITY Alliance will continue with earthworks, drainage, bridge construction, track works (including internal rail realignment), overhead electrical works and the installation of services at Clapham Yard.

Map showing Moorooka station early works.

Moorooka station early works - September and October 2024

From mid-September, early works will commence at Moorooka station ahead of major construction commencing in 2025. This will include the demolition of the building at 1137 Ipswich Road over the coming months, weather and construction conditions permitting.

Map showing the Dutton Park station work areas, rail corridor stie access points and pedestrian routes between the station and Cornwall Street.

Dutton Park station construction update - December 2024 and January 2025

In December 2024 and January 2025, works will continue with finishing touches at the station, ongoing work at Kent Street and the installation of overhead electrical structures, signaling equipment, cable routes, and drainage within the rail corridor.

Map showing pedestrian access to Rocklea station from Brooke Street and Railway Parade, Rocklea.

Completion works Rocklea station - August to September 2024

During August and September, UNITY Alliance will continue minor rectification and finishing works around the Rocklea station precinct.

Map showing work areas at Yeerongpilly station, pedestrian access and intermittent traffic changes on Wilkie Street, Yeerongpilly.

Yeerongpilly station construction update - December 2024 and January 2025

In December 2024 and January 2025, UNITY Alliance will continue to fit-out station buildings, canopies and the station entrance, landscaping and construction of the Wilkie Street commuter car parks. Major works at the station are nearing completion with the station due to reopen to customers once all works and testing and commissioning activities are complete in early-2025.

Map showing work areas, temporary traffic changes on Cowper Street/Fairfield Road and Lake Street, Yeronga and pedestrian movements around works.

Yeronga station construction update - November 2023 to January 2024

Between November 2023 and January 2024, minor finishing works at Yeronga station will continue.

Map showing work areas, temporary traffic changes on Equity Street, Fairfield and pedestrian movements around works.

Fairfield station signalling system construction update - June and July 2024

During June and July 2024, UNITY Alliance will commence works to install European Train Control System (ETCS) equipment including a signalling radio mast and equipment shelter within the rail corridor at Fairfield station.

A construction site showing a wide cavern extending into a concrete wall

Works notices

Access information on works notifications relating to construction at our Fairfield to Salisbury sites.