Current status
Procurement update
The Delivery Authority has engaged Acciona Georgiou Joint Venture (AGJV) in a collaborative Early Contractor Involvement (ECI) phase to enable a Design and Construction agreement to deliver Hope Island station. The ECI phase has commenced, and construction is planned to start in 2023.
AGJV is the head contractor delivering the Coomera Connector Stage 1 North package, located immediately adjacent to the Hope Island station. Integration and delivery of both projects under one contractor has been determined as the preferred delivery solution to reduce project interface risks including safety, construction and delivery timeframes.
The Delivery Authority will continue to work closely with the Coomera Connector Project Team, Department of Transport and Main Roads and City of Gold Coast Council throughout delivery to minimise impacts to residents and stakeholders.
For more information on the Coomera Connector Project, please visit their website.
Site establishment activities – Mangrove Jack Park
Vehicle access and car parking facilities at Mangrove Jack Park, off Hope Island Road, Helensvale, closed to the public in early 2023 to enable Acciona Georgiou Joint venture (AGJV) to establish a temporary site compound for Coomera Connector Stage 1 North.
This area of Mangrove Jack Park will also become part of the new Hope Island Station and will remain closed for the duration of construction.
Site investigations including geotechnical works, survey and utility identification activities are underway in Mangrove Jack Park in preparation for the new Hope Island Station. These investigations will be used to further inform and refine the preliminary station design.
You can find out more information about these works here.
Benefits for Hope Island
Hope Island station will provide the local community with greater access to convenient rail services; expanding options for easy travel within the Gold Coast, as well as to Brisbane.
The new Hope Island station will include the following features:
2. Provision for future car park expansion
3. Future Coomera Connector project
4. Lighting and CCTV throughout car park and station
5. Six accessible car parks
6. Two through-lifts on each platform
7. Accessible kiss ‘n’ ride bays
8. Accessible taxi bays
9. Bus stops
10. Bus parking
12. Planned connection to local pedestrian and cycle paths
13. Existing pedestrian connections
14. Station building and ticketing
15. Stairs connecting entry level to platforms
16. New signalised intersection
17. Water overflow basin
18. Existing phone tower
19. Existing sewer station
In response to strong community feedback to increase parking capacity at Hope Island, the Delivery Authority and AGJV are investigating options to enable car parking expansion to be delivered as part of a staged approach.
The Hope Island station will be located next to Mangrove Jack Park, off Hope Island Road and is scheduled to be open in time for the first Cross River Rail services to the Gold Coast.
What’s Next
The Delivery Authority is currently out to market for a contractor to finalise the design and construct Hope Island station.
Further studies are being undertaken including traffic management, hydrology, noise and environment assessments to further refine and finalise the design in preparation for construction.
The community will be kept updated as the station design is finalised and will be notified of the construction program and activities well in advance of works commencing on site.
To stay up to date with the project and to receive notifications, we encourage you to subscribe.