Hope Island station construction update - October 2024

Acciona Georgiou Joint Venture (AGJV) has been awarded the contract to design and build Hope Island station, with major construction now underway. Key construction activities to be carried out in October are outlined below.

 

Upcoming works

Construction activities planned this month include:

Civil works

  • General earthworks
  • Installation of permanent road kerbs and barriers, new underground services, drainage infrastructure and street lighting
  • Ongoing site investigation works
  • Vegetation clearing in accordance with all relevant approvals, using fauna spotter/catchers
  • Asphalt and road pavement placement

Station platform construction

  • Construction of platform columns, headstocks and plaza foundations
  • Platform deck construction
  • Platform coping stone installation will occur during planned track closures in October

Installation of platform girders

  • Platform girders will be transported to site and prepared for installation
  • Platform girder installation works

Installation of platform building structural elements

  • Platform lift shafts and precast panels will be transported to site and prepared for installation
  • Lift shaft installation works will occur outside of normal construction hours

 

Rail corridor works

Some rail corridor works are planned to occur outside the project’s normal working hours when there is reduced rail traffic to ensure works can be completed safely and efficiently. Out of hours rail corridor works are scheduled for:

  • Saturday 12 October from 5:00am to Sunday 13 October 10:00pm

 

Work area

Work area and access changes at Hope Island.

 

Construction hours

The majority of works will be undertaken between 7:00am and 5:00pm Monday to Saturday, weather and construction conditions permitting.

Due to site conditions and safety requirements, some out of hours deliveries and works will be required from time-to-time, particularly for the delivery and preparation of large construction equipment and materials, such as girders and lift shafts.

What to expect

  • Local traffic changes including lane closures and night works on Hope Island Road
  • The use of graders, excavators, trucks, cranes, compaction equipment, vacuum trucks, water carts, hand-held tools, concrete pumps, and lighting towers.
  • Construction activities may generate increased levels of noise, dust, and vibration in the area associated with the use of construction equipment. Every effort will be taken to keep noise to a minimum
  • Comprehensive management plans and onsite controls have been established to monitor and mitigate impacts of construction, such as water carts for dust suppression
  • Safety lighting and reversing squawkers will be in use, however lighting on site will be positioned away from residential properties wherever possible
  • The use of machinery including graders, excavators, trucks, compaction equipment, jackhammers and other rock breaking attachments, vacuum trucks, cranes, water carts, drill rigs, and other hand-held tools
  • Increased truck movements and workforce on site
  • Pedestrian changes in Mangrove Jack Park, as per the map below. We appreciate your patience while we work to build the new Hope Island station.

We appreciate your patience while we work to build the new Hope Island station.

Changes to the way you travel

We encourage you to consider your travel options, plan ahead and allow extra travel time by using the links below:

If you want to know more, all of this information is available in PDF form: