Merrimac station construction update - May & June 2026
Fulton Hogan is continuing major construction activities within the eastern and western rail reserves and Gooding Drive. Further construction work will also continue within the rail corridor.
Throughout May and June 2026, from 7:00am to 6:00pm (Monday to Saturday), works will include:
Eastern and western rail reserves
- Drainage works including excavation, open channel construction, concrete works, culvert and pipe installations.
- Station surface and access road construction, road pavement, surface activities and construction of bus and taxi shelters, including concrete works and steel installation.
- Works on public utilities and services, including conduit trenching, electrical activities and lighting installation.
- Ongoing earthworks activities, including stockpiling of materials, excavation, heavy vehicle movements and pre-loading.
- Sewer activities including intermittent dewatering works using pumps, including out of hours activity where required.
- Landscaping and fencing installation.
Station Building, Platforms, and Rail Corridor Activities
Key activities include:
-
Station building works, including concreting and steel works, plumbing and electrical activities, roofing installations and concrete pouring during out of hours, as required
- Lift shaft and service works, including steel and cladding installation, waterproofing and glazing works
- Station platform works, including ongoing concreting, steel installation and platform canopy roofing works
- Pedestrian overpass installation and electrical overhead connection finalisation.
- Installation of on-track and trackside signalling equipment.
Rail corridor works, including night works, are planned to occur outside normal working hours during scheduled track closures (construction and weather permitting). Rail corridor activities (listed above) will be completed during day and night shifts (24 hours) on the following dates:
- From 6:00am Saturday 20 June 2026 to 6:00pm Sunday 21 June 2026

Gooding Drive / Station Access roadworks
Roadworks in both directions will continue on Gooding Drive in 2026 (program and weather permitting).
Intermittent night works will continue throughout both May and June to facilitate centre median demolition and construction, followed by road profiling and asphalting in both directions.
These activities can only be undertaken safely at night under traffic management.
Residents located near these activities will continue to receive direct reminders prior to works.
Activities will include:
- Centre median demolition and construction, including construction of new turning lanes into the station access road.
- Demolition and installation of utilities and services, including drainage, water main, sewer and lighting, pit excavation, trenching and electrical works.
- Road profiling, asphalting, line marking activities and pavement placements
- Kerb, verge and footpath works, including ongoing concrete activities.
- Installation of fencing, road barriers and guard rail, including concrete works.
- Access road construction, including pavement and surface activities and material deliveries.
- Landscaping, traffic signalling and detector loop installation.
- Vegetation pruning and clearing in accordance with all relevant approvals, with fauna spotter/catchers in attendance.
- Reinstatement of sections of the Gooding Drive noise barrier (eastbound).
Works will be undertaken between 7:00am to 6:00pm, Monday to Friday, and 8:00am to 1:00pm Saturday (where required). Out of Hours activities will be undertaken from 7:00am to 6:00am, Monday to Sunday.

Above: kerb being poured for kiss ‘n’ ride, taxi bays and bus routes
Traffic and Pedestrian Changes
- Lane width reductions and alignment changes on Gooding Drive in both directions.
- Intermittent single lane closures, speed reductions and short-term delays on Gooding Drive in both directions, between Ghilgai Road and Bourton Road.
- Ongoing intermittent delays and changes to cyclist and pedestrian movements around Gooding Drive.
- Workers and vehicles accessing the site via Gooding Drive (both directions), Entry Drive, Crelga Court, Nisbet Place and Willunga Place.
- Intermittent parking restrictions and short-term changes to haulage routes.
What to Expect
- Construction activities may generate increased levels of heavy vehicles, noise, vibration, dust and potential odours (from asphalting) in the area. Every effort will be made to keep these changes to a minimum.
- An increase in worker and construction presence on Gooding Drive, including intermittent noise at night.
- Construction activity and heavy vehicle movements will continue to transport materials to the site via Gooding Drive (both directions), Entry Drive and Crelga Court as required.
- Intermittent use of mobile lighting towers and safety lighting within the rail reserve and Gooding Drive (both directions). Light sources will be positioned away from properties wherever possible.
- The use of machinery including elevated work platforms, trucks, excavators, concrete machinery, cranes and boom lifts, asphalt plant and rollers, line marking equipment, vibration hammers, cable hauling equipment and handheld tools.
Changes to the way you travel
Changes to the way you travel Construction of new stations on the Gold Coast line, including Merrimac, can mean changes to your travel. Consider travel options, plan ahead and allow extra time by using one of the links below:
Further Information
For more information about the project, visit Cross River Rail. You can also contact the project team by calling 1800 010 875 or emailing [email protected].
If you want to know more, all of this information is available in PDF form:
“