Salisbury station construction update - April 2024

During April 2024, UNITY Alliance will continue early works in your local area as part of the Cross River Rail, Salisbury station accessibility upgrade.

Details of work

The following activities are scheduled to occur between 6:30am and 6:30pm, Monday to Saturday during April 2024, weather and construction conditions permitting:

  • Earthworks including gravel installation works on Dollis Street
  • Constructing a stable surface for piling to commence within the rail corridor including excavation and concreting
  • Piling works for the platform 3 overpass foundations, and gantry crane in the rail corridor
  • Installation of services for platform 3
  • Drainage installation works including excavation, steel fixing and concreting
  • Service identification using vacuum trucks, and excavation for service installation.

 

Out of hours work

The following activities will occur outside the project’s normal working hours, as outlined below.

At Salisbury station and in the rail corridor and intermittently between 6:30pm and 6:30am during April 2024, the following works will occur:

  • Location of inground services including the use of vacuum trucks
  • Installation of safety barriers within the rail corridor using power tools including hammer drills
  • Delivery of materials to the rail corridor via Dollis Street, Fairlie Terrace and Lillian Avenue
  • Earthworks and drainage installation.

At Salisbury station and in the rail corridor and between 2:00am Monday 8 and 12:00am Sunday 14 April 2024, the following works will occur:

  • Earthworks including the use of excavators and vacuum trucks for new station platform early works
  • Excavation for drainage installation
  • Service identification and relocation works
  • Signalling work including the installation of overhead electrical line masts and foundations
  • Cable service relocation including trenching and installation
  • Piling for new overhead structures
  • Precast concrete panel installation and concrete works.

 

Work locations at Salisbury station April 2024

 

Map showing work areas, temporary traffic changes on Fairlie Terrace and no parking on Dollis Street, Salisbury.

 

What to expect

During these works you may notice some intermittent disruptions such as:

  • A single lane closure on Olivia Avenue, Fairlie Terrace and Dollis Street to access the rail corridor (please see map). Traffic control and signage will be in place to direct motorists, pedestrians and cyclists around work areas
  • Parking on the eastern side of Dollis Street is no longer available until completion of the Salisbury station upgrade
  • The Salisbury station pedestrian overpass will be closed from Monday 8 April to Sunday 14 April
  • Light vehicles, trucks and machinery including excavators with jackhammer and rock breaker, bobcat, vacuum trucks, soil sampling drill rig, concrete trucks, concrete pump trucks, small power tools, drills, saws, minor vibrating equipment and mobile lighting towers to light work areas at night.
  • Changes around your local area such as construction vehicles, traffic management signs and personnel
  • Increased levels of noise, vibration and dust associated with the use of heavy machinery and equipment.
  • There will be track closures and travel changes on the Gold Coast and Beenleigh lines from Friday 29 March until Sunday 14 April to undertake crucial Cross River Rail works and Queensland Rail maintenance. We encourage you to consider your travel options, plan ahead and allow extra travel time. Learn more at the dedicated webpage.

If you want to know more, all of this information is available in PDF form: