Woolloongabba station construction update - August and September 2024

At Woolloongabba station, all 24 escalators have been installed in the main station atrium and on the station platform.

Below the surface, electrical and mechanical fitout remains ongoing, including installation of fans for tunnel ventilation, permanent station lighting, platform screen door headers and glass facades, as well as the station elevators. Track floor slab concreting and rail installation continues.

Above ground, in the coming months the station steel canopy frame will be lifted and installed in three segments and stitched together above the station main entrance building.

In the wider Woolloongabba station precinct, temporary traffic changes continue for utility works on Main, Leopard, Gibbon, and other local streets. This work will enable utility services to be connected from the main service lines to the future Woolloongabba station.

 

Woolloongabba station steel canopy structure at ground level within the Woolloongabba worksite.

 

Details of work

Rail construction and tunnel fit out

Ongoing until end of project.

The below tunnelling and tunnelling support activities are undertaken 24 hours a day.

  • Installing mechanical and electrical components such as cabling, fire safety mechanisms, walkways, communication networks lighting and CCTV
  • Excavating and demolishing temporary concrete ramps in the cavern and station box
  • Mass concrete pours for track installation
  • Materials delivery associated with rail installation and fit out
  • Rail track installation within the station box.

 

Station building, services building & surface works

Ongoing until end of project

The below works will be undertaken during the standard construction hours, 6:30am to 6:30pm, Monday to Saturday. Some activities will be completed out of normal construction hours, 6.30pm to 6.30am, due to traffic permits, safety requirements and construction methodology. Nearby residents will be notified in advance via letterbox drop. Tunnelling support activities are undertaken 24 hours a day.

  • Cranes operating during day and night shifts
  • Ongoing canopy construction on ground level followed by installation above the station box using cranes
  • Precast concrete beam assembly and concrete preparation
  • Platform construction and associated structures in the south cavern, north cavern and station box
  • Installing glazing, cladding, structural steel and escalators in the main station atrium
  • Continued mass earthworks to fill the decline ramp leading down into the station box
  • Vegetation removal where required
  • Concrete deliveries for related station structure pours*
  • Cutting and fixing steel reinforcement bars and mesh
  • Ongoing concrete pours to construct the building floors and walls
  • Work to demobilise offices, crib rooms and facilities along Vulture Street within site boundaries
  • Mechanical and electrical fit out within the services building and basement levels
  • Fencing, earthworks, retention works and construction to build the retaining wall along the boundary of the Woolloongabba busway and Main Street. Detours will be in place and there will be access changes around the Woolloongabba area
  • Utility service construction conducted by Energex and Telstra on Leopard Street, Main Street and Gibbon Street. These may require temporary traffic and pedestrian changes
  • Sewer inspection, survey, geotechnical works and water monitoring in and around the Woolloongabba site as well as in Main, Leopard and Gibbon streets. Some temporary lane/road closures and pedestrian footpath detours may be required for this work. Further notification to be provided
  • Assembling and installing the station canopy structure, escalators, lift shafts, and platform screen doors (PSDs).

*Please note concrete deliveries to site are permitted 24/7.Work is subject to relevant approvals and suitable conditions.
 

Escalator installation within the main atrium of the station building

 

What to expect

  • Potential noise, dust, and vibration from construction activities both underground, in the tunnels and on the surface of the site, including outside of standard construction hours
  • Temporary lighting for out-of-hours works in the station box, decline ramp and busway work area
  • 24-hour ongoing underground work along the tunnel alignment
  • Out-of-hours deliveries of large trucks and plant. This includes mobilisation, set up and demobilisation. Short term road closures in the area may also be required
  • Continued utility investigations, surveying, geotechnical works and service relocation activities, both on and off site. Temporary pedestrian and lane detours and closures may be required to facilitate these works
  • Ongoing intermittent lane, road and footpath detours and closures at Leopard Street and Main Street
  • Full road closure on a section of Gibbon Street and Stanley Street service road. Further notification to be provided
  • Ongoing footpath closure between Main Street and Woolloongabba station platform 2 due to retaining wall works
  • Temporary footpath reopening during AFL game days between Platform 2 and Main Street – learn more here.

Work is subject to relevant approvals and suitable weather conditions.

If you want to know more, all of this information is available in PDF form:

 

Woolloongabba station design

The new underground station at Woolloongabba will provide passengers with high frequency services, as well as improved access to The Gabba Stadium and Woolloongabba’s local entertainment district.

Click here for more information about the design of the Woolloongabba station.