Merrimac station construction update - May and June 2025

Fulton Hogan is continuing major construction activities within the eastern and western rail reserves and Gooding Drive. Further construction work will also continue within the rail corridor.

Major construction

Throughout May and June 2025, works will be undertaken between 7:00am to 5:00pm, Monday to Saturday, and 8:00am to 1:00pm Sunday (where required).

Works will include:

  • Ongoing retaining wall construction, including concrete pours and back-filling
  • Ongoing platform enabling works, including screw piling, sheet piling removals, pile caps, installation and cutting of fill, concrete pours and platform steel structure installations
  • Lift shaft and services works, including concrete pours, steel installation, pile cap excavations, break back of piles and jackhammering
  • Ongoing construction of environmental management controls, sedimentation fencing and drainage channels, including culvert excavation and installation, concrete works and pipe installations
  • Ongoing ground treatment and strengthening activities
  • Ongoing works on public utilities, overhead wire transfers, shotcrete, cable hauling and conduit trenching
  • Sewer activities including environmental monitoring and ongoing surveying, as well as intermittent dewatering works using electric pumps, including out of hours activity where required
  • Ongoing minor vegetation clearing in accordance with all relevant approvals, with fauna spotter / catchers in attendance
  • Ongoing earthworks activities, including stockpiling of materials, excavation, heavy vehicle movements and pre-loading
  • Installation of on-track and trackside signalling equipment.

Gooding Drive / Station Access Road roadworks

Roadworks will continue on Gooding Drive in both directions (weather and program permitting). Works will be undertaken between 7:00am to 5:00pm, Monday to Saturday, and 8:00am to 1:00pm Sunday (where required).

Gooding Drive activities include:

  • Ongoing ground treatment and strengthening activities, including earth removal and replacement works to facilitate retaining wall construction and concrete pours
  • Demolition of existing drainage lines, footpath and kerb, to enable activities on water main connections for the future station
  • Road barrier movement and installations

Intermittent night works will continue on Gooding Drive and site entrances over the coming months. These activities can only be undertaken at night due to safety and traffic management requirements. Residents located near these activities will receive direct reminders prior to works.

Work areas and vehicle movements

Map of the Merrimac station work areas and vehicle movements along Gooding Drive.

Rail Corridor Works

From Gooding Drive overpass to Red Ash Court, rail corridor works (including night works) are planned to occur outside normal working hours during scheduled track closures, pending construction and weather permitting. Activities will be completed during day and night shifts, 24 hours day.

Works will include excavation of pile caps, concrete pouring, horizontal directional drilling, sheet piling removals, installation of steel modules for platforms, track monitoring and overhead works on the underside of the Gooding Drive bridge. Installation of on-track and trackside signalling equipment will also be undertaken.

Activities are planned on the following dates:

  • From 6:00am Saturday 17 May 2025 to 6:00pm Sunday 18 May 2025
  • From 6:00am Saturday 14 June 2025 to 6:00pm Sunday 15 June 2025

Queensland Rail will carry out track works over the June weekend, including ballast, rail cutting and resurfacing works during the day. Rail restressing works will occur at night with hand tools and hi-rail excavator.

For enquiries relating to Queensland Rail track maintenance activities, [email protected].

What to expect

  • Construction activities may generate increased levels of heavy vehicles, noise, vibration and dust in the area. Every effort will be made to keep these to a minimum
  • Construction activity and heavy vehicle movements will continue to transport materials to the site via Gooding Drive eastbound and westbound
  • Ongoing temporary changes to pedestrian access and movements around Gooding Drive (both directions) and Entry Drive
  • Ongoing intermittent parking changes on local roads
  • Intermittent daily single lane closures, speed reductions and short-term delays on Gooding Drive in both directions, between Ghilgai Road and Bourton Road
  • Traffic management and road signage will be in place to assist and direct motorists
  • Workers and light vehicles accessing site via Entry Drive, Crelga Court, Nisbet Place and Willunga Place
  • Intermittent use of mobile lighting towers and safety lighting within the rail reserve and Gooding Drive (both directions). Every effort will be made to position light sources away from properties
  • The use of machinery including trucks (including water and fuel carts), graders, excavators, vac trucks, cranes, chainsaws, drill rigs, earth moving machinery, piling rigs, rollers, chainsaws, boom lifts, concrete machinery, vibration hammers, cable hauling equipment and hand-held tools.

Changes to the way you travel

There will be track works and travel changes during May and June 2025, this includes the Gold Coast and Beenleigh lines.

We encourage you to consider your travel options, plan ahead and allow extra travel time by using the links below:

If you want to know more, all of this information is available in PDF form:

To speak with a member of the project team please contact 1800 010 875 or email [email protected].