Hope Island station construction update - September 2025

Acciona Georgiou Joint Venture (AGJV) has been awarded the contract to design and build Hope Island station, with major construction now underway.

Key construction activities to be carried out in September are outlined below

Upcoming Works

Station car park and building works

7:00am to 5:00pm Monday to Saturday, weather and construction conditions permitting

  • Asphalting, kerb and pavement placement, light pole installation and landscaping in the station carpark
  • Station building and plaza fit-out, and services installation
  • Construction and fit-out of the kiss’n’ride and bus bay areas

Station Platform works

7:00am to 5:00pm Monday to Saturday, weather and construction conditions permitting

  • Installation of pavers and screen
  • Painting, service installation and stormwater drain installation
  • Ongoing construction of the platform stairs and lift fit-out activities

Hope Island Road Works

The majority of works will be undertaken between 7:00am and 5:00pm Monday to Saturday, weather and construction conditions permitting.

Due to traffic permit requirements, ongoing works on Hope Island Road will also be completed out of hours between 7:00pm and 5:00am from Sunday to Thursday.

Some night works may also be required in the station car park to coordinate with paving and asphalting works on Hope Island Road.

  • General earthworks including excavation, rock placement and compaction
  • Installation and maintenance of underground utility services and drainage infrastructure
  • Relocation of fencing and barriers
  • Asphalt, kerb, pavement placement and line marking activities
  • Installation of the signalised intersection infrastructure (to be commissioned when station is operational)

Rail Corridor Works

Some rail corridor works are planned outside the project’s normal working hours to ensure works can be completed safely and efficiently.

Out of hours rail corridor works are scheduled from 2:00am Saturday 20 September to 10:00pm Sunday 28 September 2025

Changes to the Way You Travel

From Saturday 20 September to Sunday 12 October, there will be major track closures and travel changes on the Beenleigh and Gold Coast lines. Some journeys may take significantly longer than usual.

We encourage you to consider your travel options, plan ahead and allow extra travel time by using the links below:

Work area

Map of Hope Isalnd station construction works area.

 

What to Expect

  • Local traffic changes including intermittent lane closures and night works on Hope Island Road
  • Construction activities may generate increased levels of noise, dust, and vibration associated with the use of construction equipment. Every effort will be taken to keep noise to a minimum
  • Safety lighting and reversing squawkers will be in use; however, lighting will be positioned away from residential properties where possible
  • The use of machinery including graders, excavators, trucks, compaction equipment, jackhammers and other rock breaking attachments, vacuum trucks, cranes, water carts, and other hand-held tools
  • Increased truck movements to and from site
  • Pedestrian changes in Mangrove Jack Park and along Hope Island Road. Please follow all relevant signage.

We appreciate your patience while we work to build the new Hope Island station.

If you want to know more, all of this information is available in PDF form: