Precinct: Shorncliffe Line
Installation of signalling infrastructure – August 2025
[…]
Signalling system testing and training – August 2025
[…]
Signalling & system testing – July 2025
[…]
Signalling & system testing – June 2025
[…]
Signalling work & system testing – May 2025
[…]
Track closure on the Shorncliffe line for ETCS testing
[…]
Shorncliffe line track closures -old
[…]
Signalling work & system testing – April 2025
[…]
Signalling work & system testing – March 2025
[…]