Woolloongabba precinct traffic changes until mid-2026

As part of essential utility and service work required for the new Woolloongabba station, intermittent traffic and pedestrian changes will continue on Main, Leopard and Stanley streets until mid-2026.

Work details

  • Installing site fencing, hoarding and road safety barriers for lane and footpath closures
  • Utility and service work which may include the use of machinery including excavators, concrete saws, generators, light vehicles, lighting units, ventilation fans and hands tools
  • Kerb installation and footpath and road reinstatement.

Traffic and pedestrian changes

  • Intermittent lane closures on sections of Leopard, Stanley and Main streets
  • Footpath closures on sections of Leopard, Stanley and Main streets
  • Traffic control and detours will be in place to support motorists, pedestrians and cyclists, with vehicle access maintained in both directions
  • Access to residential properties and businesses will be maintained at all times
  • Closures will not occur during major events.

 

Traffic changes at Leopard, Stanley and Main streets until mid-2026.
Above: Traffic changes at Leopard, Stanley and Main streets until mid-2026.

Work hours

Construction activities and associated closures will occur during both day and night shifts (24/7).
Work is subject to relevant approvals and suitable weather conditions.

What to expect

  • Temporary vehicle and pedestrian detours
  • Increased truck movements and traffic control on Main Street, Stanley Street and Leopard Street
  • Increase in noise, vibration and dust associated with work
  • Increase in construction workers.

Project information

Every effort will be made to minimise the impact of this work on businesses, residents and commuters.

If you have any questions, speak to a member of the Tunnel and Stations team by call 1800 010 875.