Roma Street station construction update - June and July 2025
Roma Street station is taking shape, with both above and below ground works progressing.
Recent cladding has been installed on the canopy roof, tiling works are ongoing throughout the site, and glazing for the passenger lifts is in progress.
Installation of permanent underground services and urban realm work is ramping up near the Roma Street station site, with changes to signalised intersections and footpath upgrades scheduled to commence in the coming months.
Roma Street urban realm work
From mid-2025, urban realm work will be undertaken in the Roma Street precinct including footpath remediation, new drainage and underground services, road resurfacing and landscaping.
Further information about each package of work will be provided prior to construction commencing.
What to expect
Roma Street station construction hours are 24 hours Monday to Friday and 6:30am to 6:30pm on Saturdays unless advised. Some activities may be required to take place outside of these hours.
During construction, you may notice:
- Increased levels of noise, dust and vibration
- Construction vehicles travelling to and from the worksite via Roma Street
- Delivery of materials and equipment to the worksite including at night
- Temporary traffic and pedestrian changes on Roma Street and surrounding streets.
Main station entrance building and existing station
Roma Street – Opposite Makerston Street
The below works features both day and night work:
- Oversized deliveries to and from site and the busway including crawler crane, permanent canopy steel, mechanical and electrical equipment and architectural panelling. Deliveries may occur at night outside of operational hours
- Installation and fit-out of external cladding and architectural and glass panels
- Adjusting hoarding and scaffolding requiring hand tools and steel fixing
- Preparatory works including excavation requiring elevated work platforms, cranes, vacuum trucks and hand tools
- Intermittent short-term pedestrian stoppages, partial lane closures, footpath diversions and adjustments to pedestrian gantries along Roma Street
- Installing steel, roof sheeting, guttering and fit-out activities to construct the platform canopy
- Delivering equipment via Roma Street and the busway at night outside of operational hours
- Reconstructing platform 2 requiring a partial lane closure of the busway, installation of hoarding and traffic management barriers, demolition works, steel fixing and concreting
- Demolition of the platform 2 slab and internal walls requiring excavators, jackhammers, saw-cutting, hand tools, elevated work platforms and installation of noise proof matting
- Constructing the lift shaft and stairs requiring concrete trucks, agitators, and pumps
- Platform 1 tie in to canopy pavilion area requiring rain screen installation, scaffolding, formwork, concrete pours, structural steel delivery and steel fixing
- Pedestrian and local road changes to undertake urban realm, gantry removal and exterior building work
- Service installation on Roma Street including trenching work.
Western services building
Roma Street – Opposite Garrick Street
The below works features both day and night work:
- Testing and commissioning services including tunnel ventilation systems, communication and control systems and energisation of services
- Construction of driveway and service utility connections involving concreting activities, installation of scaffold, drainage and use of vacuum trucks
- Heavy plant movement including use of cranes and oversized deliveries to site
- Installation of façade and architectural panels requiring intermittent footpath and lane closures. Please see Roma Street – temporary eastbound lane and northern footpath closures for more information
- Concrete demolition of temporary internal walls and slabs requiring hand tools and jackhammers
- Installation of underground services from the services building to Roma Street. Further information will be provided
closer to work commencing - Commencement of service investigations and installation for sewer line and utilities on Roma Street.
Surrounding streets and footpaths
Roma, Herschel, Makerston and George streets
The below works features both day and night work:
- Installation of permanent underground stormwater infrastructure including drainage pipes, manholes and gully pits along Roma Street
- Open-cut trenching and pipe installation with road saws, jackhammers, excavators, vacuum excavation trucks, generators, mobile cranes, lighting towers and hand tools
- Upgrades to the footpath on the northern side of Roma Street. Further information will be provided closer to work commencing
- Stop-and-go traffic control arrangements, footpath closures and partial lane closures outside of standard hours
- Installation of permanent underground stormwater drainage between Parkland Boulevard and the western site boundary
- Traffic and intersection changes at the Makerston Street intersection
- Final site establishment works at the Herschel and Roma Street intersection requiring hoarding installation, vegetation removal, asset removal and the adjustment of traffic conditions for vehicles, pedestrians and cyclists. Further information will be provided prior to closure of the road to vehicles.
Underground cavern
Acoustic shed, corner of Roma Street and Parkland Boulevard
The following works features both day and night work:
- Fit-out of mechanical and electrical services, architectural panelling, ceiling material and tiling
- Commissioning of tunnel ventilation systems, communication and control systems and energisation
- Construction of egress building requiring concrete trucks and pumps.
If you want to know more, all of this information is available in PDF form: