Mayne Yard construction update - August and September 2025
In August and September 2025, works will continue in the Mayne Yard stabling facility including rock breaking, earthworks, track modifications, removal of redundant structures, installation of foundations and new masts for overhead electrical wires.
Mayne Yard East construction area in June 2025.
Details of Work
During August and September 2025, the following activities are scheduled to occur between 6:30am and 6:30pm, Monday to Saturday, weather and construction conditions permitting:
- Continue installation of fencing and inground services within Mayne Yard East
- Continue construction of the new rail bridge over Breakfast Creek
- Excavation including rock breaking, earthworks and removal of materials from site
- Road pavement works including asphalting and line marking
- Installation of foundations and masts for overhead electrical wires
- Ongoing installation of cable routes and pits within the rail corridor
- Rail track construction, including formation works, ballast placement, sleeper and rail construction, resurfacing and welding works
Out of Hours Work
Work activities in Mayne Yard (Bowen Hills) are scheduled during planned track possessions (when trains are not operating) or outside the project’s standard working hours are outlined below, weather and construction conditions permitting.
On night shift and Intermittently between 6:30pm and 6:30am throughout August and September 2025, the following works will occur:
- Concrete works including placement of formwork, steel fixing and concrete pours
- Delivery of plant and materials to site
- Installation of cable conduits and pits, and pulling new cables
- Track work and maintenance.
On day and night shift and between 2:00am Saturday 13 September to 2:30am Monday 15 September 2025, and between 2:00am Saturday 27 September to 2:00am Monday 13 October 2025, the following works will occur:
- Excavation, including rock breaking for the installation of inground services such as stormwater drainage. Please see map below for work locations
- Removal of redundant structures within the rail corridor
- Earthworks and service installation
- Track removal and installation
- Installation of masts and foundations for overhead electrical wires
- Signalling testing and commissioning, pulling cables and foundation works.
Mayne Yard construction access points and work areas
What to Expect
During these works you may notice some intermittent disruptions such as:
- Light vehicles, trucks and machinery including excavators with hydraulic hammers, augers, vacuum trucks, piling and drill rigs, concrete trucks, small power tools, minor vibrating equipment and mobile lighting towers to light the work areas at night
- Changes around your local area such as construction vehicles, traffic management signs and personnel
- Delivery trucks and workers’ vehicles entering Mayne Yard via the existing access road at Lanham Street and Mayne Road, Bowen Hills and via Grafton Street, Windsor
- Some increased levels of noise, vibration and dust associated with the use of heavy machinery and equipment
- Due to the construction of a new rail bridge, a section of Breakfast Creek near Grafton Street, Windsor has been temporarily closed to all boats / vessels until late-2025. The construction area boundaries will be marked with buoys on the water within Breakfast Creek.
If you want to know more, all of this information is available in PDF form: