Dutton Park station construction update - February and March 2025
In February and March 2025, works will continue on Kent Street and within the rail corridor including the installation of overhead electrical structures, signaling equipment, cable routes, and drainage.
Details of work
The following activities are scheduled to occur between 6:30am and 6:30pm, Monday to Saturday during February and March 2025, weather and construction conditions permitting:
- Continue Kent Street construction activities including drainage, retaining walls, footpaths, kerb and channel, and road resurfacing
- Continue works within the rail corridor including the installation of overhead electrical structures, signaling equipment, cable routes, and drainage between Ensign Avenue and the Southern Tunnel Portal
- Rectification of minor defects in the station (e.g., painting, sealing, and steel and concrete repairs)
- Ongoing maintenance of landscaping
Out of Hours Work
The following activities will occur outside the project’s normal working hours, weather and construction conditions permitting:
Location, Date and Hours of Work, Type of Work
At Kent Street and Annerley Road, and between 6:30pm and 6:30am throughout February and March 2025, the following works will occur:
- Delivery of materials to site and concrete pours
- Location of services using a vacuum truck
- Track work and maintenance
Along the rail corridor between Ensign Avenue and Kent Street and between 2:00am Saturday 22 February to 3:00am Monday 24 February 2025, between 12:10am Saturday 1 March to 3:00am Monday 3 March 2025, and between 12:00am Saturday 15 March to 3:10am Monday 17 March 2025, the following works will occur:
- Signaling and installation of foundations and masts for overhead electrical wires
- Piling for retaining wall construction near Kent Street including concrete deliveries and pours
- Drainage and earthworks in the rail corridor near Ensign Avenue
- Installation of overhead electrical structures, signaling equipment, cable routes, and pits within the rail corridor
- Cable service route installation in proximity to Kent Street, Fenton Street, and Ensign Avenue
- Earthworks to support signaling installation and under track crossings
- Track work and maintenance
Rail corridor access points, work areas and pedestrian detours during February and March 2025
What to Expect
During these works you will notice some disruptions such as:
- Access into the corridor will be via Fenton Street, Kent Street, Sampson Street, and Ensign Avenue. Traffic management will be set up to manage an increase in vehicle movements in these areas. Please follow the direction of traffic control and signage and allow for extra time to travel
- Increased noise, vibration, and dust associated with the use of heavy machinery and equipment
- Trucks and machinery including concrete trucks and pumps, frontend loaders, excavators with rock breakers, vacuum trucks, piling rig, mobile cranes, small power tools, minor vibrating equipment, and mobile lighting towers to light work areas at night
If you want to know more, all of this information is available in PDF form: