Yeerongpilly station construction update - August 2025

In August 2025, works will be undertaken adjacent to and within the rail corridor between Yeerongpilly and Moorooka stations during a scheduled track possession. Train services are operating from the island platform (platforms 2 and 3) with the new third platform (platform 1) to open at a later date. Some intermittent construction works will continue in the rail corridor.

Details of Ongoing Minor Works

The following activities are scheduled to occur between 6:30am and 6:30pm, Monday to Saturday in August 2025, weather and construction conditions permitting:

  • Under bore drilling works adjacent to the rail corridor on the corner of Wilkie Street and Station Road
  • Drainage works at the southern end of Wilkie Street including temporary traffic changes (please refer to map), excavation, concreting, compaction and asphalting
  • V-drain construction within the rail corridor including earthworks and concreting

Out of Hours Work

Work activities scheduled during planned track possessions (when trains are not operating) or outside the project’s standard working hours are outlined below, weather and construction conditions permitting, as outlined below.

At Yeerongpilly station and rail corridor and between 2:00am Saturday 23 and 2:00am Monday 25 August 2025, and between 2:00am Saturday 30 August and 10:00pm Sunday 31 August 2025, the following works will occur:

  • Cable service route installation, including excavation, drainage, and under track crossings for communications and electrical services
  • Removal old structures and installation of new masts and foundations for overhead electrical lines
  • Signal testing and commissioning.

 

Yeerongpilly station work areas and traffic changes

Map showing work areas in the Yeerongpilly rail corridor.

 

What to Expect

During these works you may notice some disruptions such as:

  • Light vehicles, trucks and machinery including excavators with rock breakers and jackhammers, loaders, mobile cranes, trucks, vacuum trucks, concrete trucks, pump trucks, loaders, cutting equipment, power tools, generator to power mobile site offices (day and night) and mobile lighting towers to light work areas at night
  • Increased noise, vibration and dust associated with the use of heavy machinery and equipment.

We appreciate your patience during construction and will continue to update you as work progresses.

If you want to know more, all of this information is available in PDF form: