Yeerongpilly station construction update - December 2025 and January 2026

In December 2025 and January 2026, works will continue adjacent to and within the rail corridor between Yeerongpilly and Moorooka stations.

Details of Works

The following activities are scheduled to occur between 6:30am and 6:30pm, Monday to Saturday in December 2025 and January 2026, weather and construction conditions permitting:

  • Under bore drilling works adjacent to the rail corridor on the corner of Wilkie Street and Station Road
  • Overhead electrical line removal and installation works, removal and installation of electrical bonds
  • Installation of service pits and conduits within the rail corridor including excavation, earthworks and concreting
  • Drainage works at the southern end of Wilkie Street including temporary traffic changes (please refer to map), excavation, concreting, compaction and asphalting.

Out of Hours Work

Work activities scheduled during planned track closures (when trains are not operating) or outside the project’s standard working hours are outlined below, weather and construction conditions permitting.

At Yeerongpilly station and in the rail corridor, and between 12:00am Saturday 6 and 3:10am Monday 8 December 2025, between 2:00am Saturday 13 and 2:00am Monday 15 December 2025, between 2:00am Saturday 20 and 2:00am Monday 22 December 2025, and between 2:00am Saturday 3 to 10:00pm Monday 26 January 2026, the following works will occur:

  • Cable service route installation, including excavation and under track crossings for communications and electrical services
  • Track works including earthworks
  • Excavation, compaction and concreting for the installation of stormwater drainage with temporary traffic changes on Wilkie Street / Station Road (refer to map)
  • Removal old structures and installation of new masts and foundations for overhead electrical lines
  • Signal testing and commissioning.

Yeerongpilly station work areas and traffic changes

Map showing work areas, temporary traffic changes on Wilkie Street, Yeerongpilly

What to Expect

During these works you may notice some disruptions such as:

  • Intermittent traffic holds on Wilkie Street between Crichton Street and Station Road to allow construction traffic in and out of the rail corridor between Saturday 3 and Sunday 11 January 2026
  • Trucks and machinery including concrete trucks and pumps, frontend loaders, excavators with rock breakers, vacuum trucks, piling rig, mobile cranes, small power tools, minor vibrating equipment, generator to power mobile site offices (day and night) and mobile lighting towers to light work areas at night
  • Increased noise, vibration and dust associated with the use of heavy machinery and equipment.

If you want to know more, all of this information is available in PDF form: