Dutton Park station construction update - June and July 2025
In June and July 2025, works will continue on Kent Street and within the rail corridor including the installation of overhead electrical structures, signalling equipment, cable routes, and drainage.
Access to the station and platforms is via stairs and lifts from the Annerley Road and Noble Street station entries. Due to ongoing construction works north of Annerley Road, access via Kent Street will open at a later date.
Details of work
The following activities are scheduled to occur between 6:30am and 6:30pm, Monday to Saturday during June and July 2025, weather and construction conditions permitting:
- Continue Kent Street entrance construction activities including drainage, footpaths, kerb and channel and road resurfacing
- Continue works within the rail corridor including the installation of overhead electrical structures, signalling equipment, cable routes and drainage between Ensign Avenue and the Southern Tunnel Portal
- Earthworks and drainage near Ensign Avenue.
Out of Hours Work
The following activities will occur outside the project’s normal working hours, weather and construction conditions permitting.
At Kent Street and Annerley Road, and between 6:30pm and 6:30am throughout June and July 2025, the following works will occur:
- Delivery of materials to site and concrete pours
- Location of services using a vacuum truck
- Track work and maintenance.
Along the rail corridor between Ensign Avenue and Kent Street, and between 12:10am Saturday 7 June to 3:00am Monday 9 June 2025, and between 12:00am Friday 27 June and 2:00am Tuesday 15 July 2025, the following works will occur:
- Installation of foundations and masts for overhead electrical equipment and wires
- Excavation, earthworks and drainage in the rail corridor between the Wilkins Street pedestrian overpass and Kent Street
- Noise barrier construction at the end of Sampson Street
- Installation of signalling equipment, cable routes and pits within the rail corridor
- Cable service route installation in proximity to Kent Street, Fenton Street and Ensign Avenue
- Excavation and earthworks to support signalling installation and under track crossings
- Track work and maintenance.
Along the rail corridor between Ensign Avenue and Kent Street, and between 6:00pm Tuesday 15 July and 2:00am Saturday 19 July 2025, the following works will occur:
- Test trains running between Dutton Park and Salisbury stations to test signalling equipment on all lines
- Signal testing and commissioning.
Dutton Park precinct rail corridor access points, work areas and pedestrian detours – June and July 2025
What to Expect
During these works you will notice some disruptions such as:
- Access into the corridor will be via Fenton Street, Kent Street, Sampson Street and Ensign Avenue. Traffic management will be set up to manage an increase in vehicle movements in these areas. Please follow the direction of traffic control and signage and allow for extra time to travel
- Increased noise, vibration and dust associated with the use of heavy machinery and equipment
- Trucks and machinery including concrete trucks and pumps, frontend loaders, excavators with rock breakers, vacuum trucks, piling rig, mobile cranes, small power tools, minor vibrating equipment and mobile lighting towers to light work areas at night.
If you would like to speak with a member of UNITY Alliance Project Team about these planned works, please contact 1800 010 875 or email [email protected] anytime for more personalised consultation.
We appreciate your patience during construction and will continue to update you as work progresses.
If you want to know more, all of this information is available in PDF form: