Boggo Road and Southern Area construction update - June and July 2024

At Boggo Road station, underground works are continuing including the installation of rail track and platform screen door frames. The station box is taking shape ahead of escalator delivery while above ground construction of the main station building progresses. The Southern Portal dive structure nears completion.

 

Pedestrian and cycle bridge update

The bridge substructure is now structurally complete and ready for installation of steelwork supporting the pedestrian access stairs and elevators. Over the coming months, painting and instillation of the protection screen frames will take place. Works to pour the concrete deck slab which will form the surface of the future walkway will be ongoing via Joe Baker Street.
 

Boggo Road station update

In the cavern, rail track, platform screen door frames, and services are being installed. Within the station box, construction of the internal and exterior walls is progressing ahead of escalator delivery and installation. Above ground, construction of the new main station building is continuing, with the construction of the canopy roof structure to commence later this year. Delivery of precast concrete units, escalator segments and structural steel will be ongoing via Joe Baker Street, requiring intermittent stop and hold traffic arrangements.

Adjacent to the Eastern Busway, excavation within the site boundary will be carried out to install new utilities and construct a retaining wall. To complete this work, site boundary barriers will be adjusted requiring temporary partial lane closures of the busway during night shift under the direction of traffic control. During this work, the busway will remain operational and pedestrian movements through the precinct will be unaffected.
 

Main station building above ground-level.
Main station building above ground-level.
 

Southern Portal update

As the Southern Portal tunnel dive structure approaches completion, track slabs are now installed and rail track is being laid.
Mechanical and electrical fit-out works continue including installation of firefighting water piping, cable trays, cabling and service walkways.
 

Extended rail closures:

There will be track closures and travel changes on the Cleveland, Gold Coast and Beenleigh throughout June and July including: 1 and 2 June and between 15 June and 7 July 2024 to undertake crucial Cross River Rail works.

We encourage you to consider your travel options, plan ahead and allow extra travel time by using any of the links below:

 

Boggo Road construction

Boggo Road to Joe Baker Street

The below works are ongoing and features both day and night work:

  • Formwork, concrete pours, and steel fixing and steel reinforcement within the station box.
  • Concrete pours scheduled overnight or in the early hours of the morning
  • Crane lifts and movement of large plant
  • Delivery of equipment and materials including large precast concrete segments and permanent structural steel via Boggo Road, Joe Baker Street and Peter Doherty Street requiring stop and hold traffic arrangements
  • Mechanical and electrical service fit-out within the station box and delivery and installation of rail track and platform screen doors
  • Excavation and installation of utility connections into service pits adjacent to the eastern busway requiring site boundary barrier adjustments and partial lane closures
  • Construction of a new retaining wall adjacent to the Eastern Busway.

 

Progress shot of Boggo Road station cavern.
Progress shot of Boggo Road station cavern.
 

Southern Portal construction

Kent Street to Railway Terrace

The below works are ongoing and features both day and night work:

  • Crane lifts and movement of large plant and machinery
  • Installation of rail infrastructure within the rail corridor
  • Mechanical and electrical service fit-out including installation of cable trays, cable pulling and service walkways
  • Delivery of equipment and materials including large precast concrete segments and permanent steel via Kent Street
  • Intermittent road and shared user pathway closures on surrounding streets
  • Service pit inspections and utility connection works on Kent Street and Railway Terrace.

 

Pedestrian and cycle bridge construction

Peter Doherty to Kent Street

The below works are ongoing and features both day and night work:

  • Ongoing works including deck concrete pours, installation of safety frames and screens, overhead canopy segments, and handrails
  • Out-of-hours concrete pours
  • Delivery of equipment and materials via Boggo Road, Joe Baker and Peter Doherty Street in the west plus Kent Street and PA Hospital access road in the east
  • Intermittent road and shared user pathway closures on surrounding streets
  • Vegetation removal and pruning work on Railway Terrace, Dutton Street, Pound Street and Peter Doherty Street adjacent to the eastern bridge approach.

 

Pedestrian and cycle bridge substructure complete.
Pedestrian and cycle bridge substructure complete.
 

Underground service inspection

Park Road station

The below works are ocurring during June 2024 and will occur during the day:

  • Inspecting and cleaning underground services with a vacuum excavator

 

General construction hours:

  • Boggo Road station construction hours are 24 hours Monday to Friday and 6:30am to 6:30pm on Saturdays unless advised
  • Southern Tunnel Portal and pedestrian and cycle bridge construction is undertaken 24 hours, seven days a week. This includes work during weekend rail corridor closures.

What to expect during construction:

  • Increased levels of noise, dust and vibration
  • Construction vehicles travelling to and from the worksite via Boggo Road, Joe Baker Street and Peter Doherty Street, Rawnsley Street, Railway Terrace, Dutton Street and Kent Street
  • Delivery of materials and equipment to the worksite at night
  • Extended concrete pours scheduled to start early in the morning
  • Temporary closures of local streets including Kent, Joe Baker and Peter Doherty streets
  • Potential short-term disruption to utility services. Additional notification will be provided if impacts are expected.

 

If you want to know more, all of this information is available in PDF form:

You can use the below details if you’d like to speak to a member of the Cross River Rail Tunnels and Stations team: