Boggo Road and Southern Area construction update - February and March 2025
The Boggo Road and Southern Area teams are progressing with construction of the new Boggo Road station and southernportal. In December, the roof canopy installation continued with 195 canopy pieces installed and approximately 500 remaining. Station fit-out is also well underway, with the installation of blockwork inside internal rooms underground continuing.
Approximately 85% of the platform screen doors have been installed at platform level, and only two escalators left to install. Installation of artwork has also commenced
External scaffold will be removed from the station structure which will sit at the final height of 20 metres from ground-level and will be completed in early 2025.
Concrete pours for the Yamma Bridge western ramp are ongoing and will continue throughout 2025. Fit-out works, including the installation of the overhead canopy, lifts, lighting, and handrails will also progress this year.
Station box – canopy installation
Boggo Road construction
Boggo Road to Joe Baker Street
The below works are ongoing and features both day and night work:
- Formwork, concrete pours, steel fixing and steel reinforcement within the station box and above
ground level - Concrete pours requiring compressor, concrete pumps, agitators, concrete vibrators and temporary
intermittent stop-and-hold traffic arrangements - Delivery of equipment and oversized materials via Boggo Road, Joe Baker Street and Peter Doherty
Street requiring stop and hold traffic arrangements, movement of plant and crane lifts - Mechanical and electrical service fit-out within the station box and delivery and installation of escalator segments, permanent structural steel, platform screen doors and blockwork
- Excavation and installation of utility connections into service pits adjacent to the Eastern Busway requiring site boundary barrier adjustments and partial lane closures
- Construction of a new retaining wall adjacent to the Eastern Busway.
Underground internal room
Southern Portal construction
Kent Street to Railway Terrace
The below works are ongoing and features both day and night work:
- Crane lifts, movement of large plant and machinery including delivery of equipment and materials via Kent Street and Railway Terrace
- Installation of rail infrastructure within the rail corridor connecting to the dive structure
- Mechanical and electrical service fit-out including installation of cable trays, cable pulling and service walkways
- Service pit inspections, utility maintenance and road works including landscaping, vegetation removal, kerb reinstatement and asphalting requiring intermittent road and shared user path closures on Kent Street and Railway Terrace
- Retention basin excavation/ Drainage works have commenced within the rail corridor at final locations.
Dutton Park precinct and Yamma Bridge.
Pedestrian and cycle bridge construction
Peter Doherty to Kent Street
The below works are ongoing and features both day and night work:
- Ongoing works including deck concrete pours, installation of safety frames and screens, overhead canopy segments, and handrails
- Concrete pours requiring concrete pumps, agitators and vibrators
- External and internal painting of the bridge requiring sandblasting equipment, scaffolding and containment sheeting, and changed traffic conditions
- Delivery of equipment and materials via Boggo Road, Joe Baker and Peter Doherty Street in the west, as well as Kent Street and PA Hospital access road in the east
- Intermittent road and shared user pathway closures on surrounding streets
- Landscaping, vegetation removal and pruning work on the western approach adjacent to Peter Doherty Street and the eastern approach adjacent to Kent Street.
General construction hours:
- Boggo Road station construction hours are 24 hours Monday to Friday and 6:30am to 6:30pm on Saturdays unless advised.
- Southern Tunnel Portal and pedestrian and cycle bridge construction is undertaken 24 hours, seven days a week. This includes work during weekend rail corridor closures.
What to expect during construction:
- Increased levels of noise, dust and vibration
- Construction vehicles travelling to and from the worksite via Boggo Road, Joe Baker Street and Peter Doherty Street, Rawnsley Street, Railway Terrace, Dutton Street and Kent Street
- Delivery of materials and equipment to the worksite at night
- Extended concrete pours scheduled to start early in the morning
If you want to know more, all of this information is available in PDF form: