Albert Street station construction update - April to May 2023

Construction of the future station buildings at the main station entrance site (Lot 1) and northern station entrance site (Lot 3) is progressing with concreting, steel fixing and site facility adjustments.

In March, the team reached a significant milestone completing the permanent concrete arch lining in the underground cavern. Back of house construction continues as mezzanine beams are delivered and installed.

 

Lot 1 – Main station entrance site (corner Mary and Albert streets)

The below works will occur within the standard construction hours of 6:30am to 6:30pm, Monday to Saturday.

Some activities will be completed out of normal construction hours due to traffic permits, safety requirements and construction methodology.

Works at Lot 1 will include:

  • Large concrete pours (requiring night work and early mornings) involving concrete trucks and pumps parked on Mary Street, and Albert Street near Charlotte Street.
  • Cutting and fixing steel reinforcement bars and mesh.
  • Transport of materials, equipment and machinery.
  • Slipform and jumpform installation including anchor drilling.
  • Utility, survey and geotechnical work including potholing.
  • Site facility adjustments.
  • Tower crane installation (more information to be provided prior to work commencing).

 

Internal wall being constructed with formwork supports
 

Construction of the main station entrance building – concreting activities

Did you know concrete has been used as a preferred construction material since prehistoric times? To date, over 5,300m³ of structural concrete has been placed at the Lot 1 site, which is equivalent to filling approximately 265 residential swimming pools (with 20,000L capacity).

As the station building continues to rise, concreting activities will increase in frequency and duration, with several large
concrete pours required over the coming months. Pours will generally start in the early morning and continue into night shift.
You may also experience increased levels of noise associated with the use of concrete trucks and pumps located on Albert Street and Mary Street.

 

Lot 2 – Tunnelling and support activities within the acoustic shed and in the underground cavern

The below tunnelling and tunnelling support activities are undertaken 24 hours a day, 7 days per week.

  • Installing formwork, steel fixing and concreting activities underground.
  • Service adjustments within the tunnel.
  • Transport of materials, equipment and machinery.
  • Back of house fit-out including installing blockwork.
  • Delivery and installation of precast mezzanine segments and platform culverts.

 

QIC – 101 Albert Street Development Application

On Friday 10 March, QIC announced they have submitted a Development Application for 101 Albert Street, which is the current location of the Cross River Rail ‘Lot 2’ construction site.

Further information in relation to this Development Application can be found on the State Development, Infrastructure, Local Government and Planning website under Current Applications and Approvals.

 

Lot 3 – Northern station entrance site (142 Albert Street)

The below works will occur within the standard construction hours of 6:30am to 6:30pm, Monday to Saturday.

Some activities will be completed out of normal construction hours due to traffic permits, safety requirements and construction methodology.

Work to construct the station building will include:

  • Large concrete pours (requiring night work and early mornings) involving concrete trucks and pumps parked on Albert Street near Charlotte and Elizabeth streets.
  • Installing jumpform to construct the building.
  • Cutting and fixing steel reinforcement bars and mesh.
  • Transport of materials, equipment and machinery.
  • Relocating tower crane (more information to be provided prior to works commencing).
  • Setting up a temporary mobile crane.
  • Site surface excavation works.
  • Site facility adjustments including partial gantry removal and site office changes.
  • Temporary structure demolition including slab, retaining wall, piles and capping beam.

 

Construction of the northern station entrance building – tower crane changes

Over the coming months, demolition of temporary structures no longer required, excavation and tower crane changes are required to facilitate the next stage of construction.

The current tower crane will be removed from site and a new tower crane will be constructed in a new location within the station box using temporary mobile cranes.

Temporary structure demolition and excavation will occur both during the day and at night, and will include:

  • Protection slab demolition including excavation of material underneath the concrete
  • Upstand wall, tower crane slab and capping beam demolition including saw cutting and jackhammering.

 

Local streets

The below works will occur within the standard construction hours of 6:30am to 6:30pm, Monday to Saturday.

Some activities will be completed out of normal construction hours due to traffic permits, safety requirements and construction methodology.

The below works will occur along Albert Street between Alice and Queen streets and includes Elizabeth, Charlotte and Mary streets:

  • Installing, maintaining and removing monitoring equipment and services.
  • Utility, borehole and geotechnical investigations and maintenance
  • Vegetation maintenance.
  • Permanent service and utility connections.

Map of Albert Street works area.

 

What to expect

During construction of the new station buildings and underground platform, there will be an increase in workforce and vehicles at the three Albert Street sites for the transport of materials, equipment and machinery.

Nearby residents and businesses may also experience an increase in dust, noise and vibration.

For your safety, intermittent temporary pedestrian and traffic holds and diversions will be in place near the worksites during concrete pours and other deliveries to the sites. Please follow all directions of traffic controllers.

If you want to know more, all of this information is available in PDF form:

 

Register for SMS alerts of controlled blast times

To receive SMS alerts prior to controlled blasts, scan the QR code or send your name and mobile number to [email protected]