Salisbury station construction update - April 2025

In March 2025, UNITY Alliance continued with the installation of platform services, pedestrian overpass, and installation of structural steel for the pedestrian overpass and station canopies.

During April 2025, construction of the station platforms, service installations, pedestrian overpass fit out and station canopies construction will continue.

Details of Work

The following activities are scheduled to occur between 6:30am and 6:30pm, Monday to Saturday during April 2025, weather and construction conditions permitting:

  • Continue installation of platform inground services and drainage including excavation, steel fixing and concreting
  • Continue installation of structural steel for station lifts and pedestrian overpass structures
  • Commence installation of structural steel for the platform 1 and 2 shade canopies
  • Commence fit out for the platform 3 shade canopy.

Out of Hours Work

The following activities will occur outside the project’s normal working hours, as outlined below.

At Salisbury station and in the rail corridor, and intermittently between 6:30pm and 6:30am during April 2025, the following works will occur:

  • Earthworks and installation of services including the use of vacuum trucks and excavators
  • Formwork and concrete works for the new station platform, including excavation for footings and slab foundations
  • Installation of structural steel and roofing install for canopies.

At Salisbury station and in the rail corridor, and between 2:00am Friday 18 and 2:00am Tuesday 22 April 2025, the following works will occur:

  • Cable service relocation works and under track crossings for services (e.g., electrical, water) including trenching
  • Formwork and concrete works for the new station platform, including excavation for footings and slab foundations
  • Install structural steel for platforms 1, 2, and 3
  • Earthworks and installation of drainage and service
  • Installation of structural steel for the station overpass including the use of mobile cranes.

 

Work areas and pedestrian access at Salisbury station

Map showing work areas, temporary traffic changes on Fairlie Terrace and Dollis Street, Salisbury.

What to Expect

During these works you may notice some intermittent disruptions such as:

  • Intermittent single lane closures on Fairlie Terrace, Lillian Avenue and Dollis Street to enable construction vehicles to access the rail corridor. Traffic control and signage will be in place to direct motorists, pedestrians and cyclists around work areas
  • Light vehicles, trucks and machinery including excavators with jackhammer and rock breaker, bobcat, vacuum trucks, trucks, concrete pump trucks, mobile cranes, small power tools, drills, saws, minor vibrating equipment and mobile lighting towers to light work areas at night and generator to power site offices (day and night)
  • Changes around your local area such as construction vehicles, traffic management signs and personnel
  • Increased levels of noise, vibration and dust associated with the use of heavy machinery and equipment.

We appreciate your patience during construction and will continue to update you as work progresses

If you want to know more, all of this information is available in PDF form: