Shorncliffe Line: Trackside signalling work
From late August 2020, Hitachi Rail will commence trackside construction work along the Shorncliffe Line to deliver Brisbane’s new railway signalling system as part of the Cross River Rail Project.
Details of work
Work will commence in late August and continue throughout September along the Shorncliffe Line to deliver a new railway signalling system.
Construction activities are scheduled to occur between Nudgee and Shorncliffe stations between 7.00am and 5.00pm, weather permitting.
Activities will include:
- Cleaning existing cable route and installing new cabling
- Laying foundations and installing signalling equipment and equipment housing.
To ensure the safety of workers and the community, some activities will be completed out-of-hours between 8.00pm and 4.00am. Where possible, work will be rotated between locations to minimise continuous activities at the same location.
What to expect if you live alongside the rail corridor
Residents along the rail corridor may see and hear:
- Movement of personnel and construction vehicles (including light and heavy vehicles, plant, machines and equipment)
- The use of lighting towers
- Noise, dust and vibration due to construction activities including trenching, use of vacuum trucks, earthworks, compacting and concreting.
To minimise impacts:
- Noise minimisation practices will be adopted in relation to the use of vehicles and machinery after hours (e.g. using lower powered machines which are quieter), while personnel noise will be kept to a minimum.
- Lighting towers will be directed away from residential properties, where practical.
- Soil disturbance will be minimised by watering down, modifying work methods on high wind days, and using dust suppression techniques if required.
- All workers will be briefed on key community and environmental considerations in relation to noise, dust, lighting, access, and parking.
We appreciate your patience during construction and will continue to update you as work progresses.
What to expect if you’re a commuter
To undertake this work safely, some track closures will be necessary. These will be scheduled at non-peak times and over selected weekends to minimise any inconvenience. Bus services will replace trains in instances where services are impacted.
Notices will be placed at affected train stations notifying customers of any changes to scheduled services. If travelling after peak on weeknights or on weekends, plan your journey by visiting translink.com.au, calling 13 12 30 or downloading the TransLink app.